Barnet Elizabethans RFC

Remodelling & Drainage of a Natural Turf Rugby Union Pitch

Client Type: Community

Contractor: ATB Sports Solutions

Overall Budget: £85,000.00

Funder: Sport England and Partnership funding

Project Goals:

  • To improve surface levels
  • To improve the drainage status of the pitch
  • To increase hours of usage per week

Key Technical Issues:

  • Uneven gradients and significant depressions
  • Poor infiltration rates
  • Compacted ground conditions

Design Solutions:

  • Earthworks (Cut and Fill) to produce gradients within Sport England/RFU guidelines
  • Installation of a primary and secondary drainage scheme
  • Enhanced agronomic maintenance

Project Outcome

  • A much improved pitch capable of providing between 3-6 hours of usage per week, a distinct improvement on previous conditions.  A much improved maintenance scheme has ensured continued good agronomic practice in sustaining natural turf surfaces for sport.